Structural steel reuse is currently pretty rare in projects in Canada, but the Centre Block rehabilitation on Parliament Hill in Ottawa is an example of a massive project with a sustainable focus.
In her presentation, Practical Considerations for the Reuse of Structural Steel at the Canadian Institute of Steel Construction conference in Toronto, structural engineer Isis Bennet, CENTRUS Joint Venture at WSP Canada Inc., used the project as a case study.
âIn the upper levels there is some steel that needs to be removed in order to facilitate this rehabilitation,â said Bennet.
âThis steel that is being removed is what weâve identified as a big opportunity to take the steel out where it needs to be demolished and bring it back to this exact same project in the new construction phase.â
The reason for doing it, she said, is embodied carbon.
âWe have about 625 tonnes of CO2 equivalents, so thatâs embodied carbon thatâs being retained on the project,â said Bennet. âFor the material that canât be reused in the Centre Block project weâve identified some of that for reuse on future projects. Of course some needs to be sent to recycling.
âThe members that are being removed from the building and brought back, weâve identified 1,700 that we will be reusing on this project.â
Before the team started the reuse initiative, they looked at the condition of the existing building.
âWe needed some verification that the steel is in good condition, that the steel that we are finding on site matches the historic drawings, so we have confidence in the design and extending the life,â said Bennet.
âWe need to test the steel to figure out what properties we should use when weâre designing. For the steel samples that were taken, we ended up deciding that we were going to design to 210 MPA.â
The team is doing a pre-selection process to identify members that have a high potential for reuse.
âIf theyâre too shallow theyâre going to have a lower capacity, less potential for reuse,â Bennet explained. âWeâre excluding members that are in built up sections. You donât want somebody to have to go in and assess whether or not the rivets along the length of the built up member are in good condition. Itâs not a good use of our resources. Weâve created this subset. Weâre identifying that on our demolition drawings so they can know what members to be careful with and which ones not to be.â
Once they know what members have met that criteria, inventory will be delivered to the design team and they will decide what goes in Centre Block and what goes into storage.
The project is currently in the deconstruction phase.
âWeâve already released our specs, how to work with this steel, how it should be inspected and weâre starting demolition,â Bennet explained. âEach member is going to have a bar code. Weâre going to be able to track that from it being removed from the building into the new construction phase where itâs installed.â
They have also identified some very simple dismantling methodology.
âKeep the members in one piece, cut it as close to the ends as possible, 50 millimetres from the supports and then weâre removing all the connectors along the length so we have a nice smooth beam,â said Bennet.
âWe are adding some storage requirements because we want these members to be protected from the elements. We donât want them to degrade while were waiting for this to be built. Weâve also informed the fabricator that this is what weâre doing. Weâre telling them the steel is 210 MPA and they need to design connections accordingly.â
Once all the beams have passed inspection, they are then passed to the design team which will try to keep it as simple as possible, Bennet said.
âWeâre designing the beam the way we normally would,â she noted. âWe have a new beam that has been designed, the target beam, and then we are looking for matches between salvaged steel inventory and these target beams, so where can we substitute this in? A pretty simple way to do that is just cross reference the capacities. Is the salvaged beam equal to or greater in capacity to the target beam?â
She admits that might raise a few eyebrows because the salvaged beam has a lower strength.
âIs this beam going to be a little bigger? Potentially, yes,â she said. âWeâre going to have deeper sections in a lot of locations, so we need to consider this in the design and identify what beams have a depth limit.â
She pointed out although there are costs associated with reusing members, the cost of new steel also exists, so the cost to offset substituting reused steel for new steel actually pays for itself and becomes cost neutral.
Going forward she said itâs important to make it easier for designers to reuse steel on projects.
âFrom my perspective, I see an industry that needs a supplier, so I can order reused steel the same way I do new steel,â she said, adding standardization is also needed.
âItâs important to figure this out to spur more steel reuse.â
Follow the author on Twitter .
Recent Comments